Homer Glen · Wastewater Treatment Plant
Per the Illinois EPA’s summary of the Village’s plan:$16 millionto serve one business —and 114 homes not built yet
Those are the customers the state’s summary projects: the one business Lockport treats for the Village today, and 114 homes it says will be developed within the next five years. The Village’s own video says the first phase is sized for about 2,500 residents. It puts the project at $15,968,320 and projects a flat sewer bill of $105 a month for those homes in 2030, rising to $125. To repay the loan it counts on those bills, a per-1,000-gallon charge to commercial users, and a “proposed Village subsidy” of $561,135 in the first year — a subsidy the Village’s February video never mentions. That video told residents the plant would be paid for by “future growth and not current Illinois American Water customers”; the summary doesn’t say where the subsidy money comes from. The plant is a real need, and Heidi is not asking the Village to cancel it. So far as we can find, the bill and the subsidy have reached residents only as scanned state pages — in a 147-page hearing packet, and on slides at the July 8 hearing, where no one read them aloud. Here is what the record shows, with a link to every source.
Exhibit A
The numbers in the state’s summary
In June 2026 the Illinois EPA summarized the Village’s plan for a state loan to build the plant — its cost, its financing, its customers and their bill — working in part from the Village’s own September 2025 project plan. The Village attached that summary to the packet for its July 8, 2026 public hearing, as scanned pages with no searchable text.
| Year | Flat rate per home, per month | Village subsidy |
|---|---|---|
| 2030 | $105 | $561,135 |
| 2031 | $108 | $476,121 |
| 2032 | $110 | $389,410 |
| 2033 | $115 | $278,978 |
| 2034 | $120 | $169,458 |
| 2035 | $125 | $42,859 |
| Subsidy, 2030–2035 | $1,917,961 | |
Where Heidi stands
This is very likely a genuine, necessary infrastructure project — Heidi isn’t asking the Village to stop it. What she is asking for is what still hasn’t happened: explain the cost, the loan and the projected bill to residents in plain language, on the plant’s own page on the Village website and in the Village newsletter; explain the proposed Village subsidy — where the money comes from, how it fits the Village’s word that growth pays for the plant, and what happens if fewer than 114 homes connect; give residents on septic an answer in writing; and set the Village sewer rate in public, with the math shown, because the same Board that approves the plant sets that rate by ordinance. The numbers exist. Residents shouldn’t have to find them as scanned pages in a hearing packet.
Exhibit B
Who the plant is for
The Illinois EPA summary says the plant “will serve” the commercial customers Lockport treats today “as well as 114 residential units that will be developed within the next 5 years,” and counts its projected customers as 114 homes and one business. It prints that count just below its rate and subsidy table. Under the heading “How is the monthly residential rate/cost of service calculated?” it names the pieces (a flat residential rate, a per-1,000-gallon commercial charge and a Village subsidy) but shows none of the arithmetic: no revenue by year, no connection schedule, and nothing on why the subsidy falls from $561,135 to $42,859. Homes on septic, it says, can connect “when they are ready.”
At the July 8 hearing, Village Engineer Brett Westcott said the plant “is not being designed to serve existing customers who are served by Illinois American” wastewater plants. Its planning area, he said, runs from the plant site out to Parker Road — “this largely undeveloped area and unserved area.” A consultant’s January 2, 2025 proposal in the Village’s Board packet describes the same area as “generally bound by 151st Street, 159th Street, Gougar Road, and Parker Road.”
The plant starts at 0.25 million gallons a day, planned to grow to 0.5 once it reaches 80% capacity; the Village’s February 2026 video says the first phase will serve “about 2500 residents” and that at full buildout the plant would serve about 3,000 acres. Its site is about 30 acres at 159th Street and Gougar Road, bought for $4,000,000 in October 2024. And the $2,591,009.72 Cedar Road sewer extension the Board awarded on June 10, 2026 — paid from the same budget account as the plant — runs into this same area.
- Village of Homer Glen
- Fiddyment Creek sewer area, drawn approximately from the Village Engineer’s description and a proposal in the Village’s Board packet
- Plant site, 159th & Gougar
Village boundary © OpenStreetMap contributors (ODbL). Service area drawn from the Village Engineer’s July 8, 2026 description and a consultant’s January 2, 2025 proposal in the Village’s January 22, 2025 Board packet — a description, not a parcel line. More on the sewer extension.
How do we know those 114 homes will be built?
The state summary doesn’t say. It never says where the 114 homes are, who would build them, or whether anyone has approved them, and we found no mention of the number in the recording of the July 8 hearing.
The only 114-home plan we found in the Village’s own records is in a June 2023 draft feasibility study by Robinson Engineering, which the Village has posted on its website. Its table of “Anticipated Short Term Population Growth in Service Area” lists about 50 acres on 159th Street east of Cedar Road as a “Conceptual Site Plan showing 114 residential Lots, no commercial” — on the stretch of 159th Street that the $2.6 million Cedar Road sewer extension was awarded to serve. The study called its table “a possible short-term forecast of development” whose buildout “would likely take at least the next several years.” The number matches; the state summary doesn’t say whether that is where its 114 came from.
Three years later, the 50 acres in that table are still vacant: the Village’s June 2026 bid memo describes the parcels its new sewer will reach, along the north side of 159th Street, as “currently unserved vacant parcels,” and we found no zoning request, subdivision plat or Village approval for homes on that land in Plan Commission or Village Board agendas from January 2024 through September 2026. (A separate, larger plan on the south side of 159th — Dunn Farm, proposed at 241 homes and later cut to 217 — has been to Village workshops in April and October 2025; we found no approval for it.) The Village’s own consultant gave an answer in 2023, in the same study: developers had approached the Village, but it was “limited in its ability to process development applications” without “economical and long-term infrastructure being readily available.” So the homes may well follow the pipe. But the state summary counts on them within five years, and beyond a line that the Village “will reevaluate the projected user rates once actual costs are known,” it doesn’t say what happens to the bill or the proposed subsidy if they come slower — or not at all.
Whose sewer bill this is
It depends on whose sewer you are on. If Illinois American Water handles your sewage — it runs three wastewater plants inside Homer Glen — the Illinois Commerce Commission sets that rate, and the Village’s own video says this project will not affect existing Illinois American Water customers. If you are on septic, you have no sewer bill today, but you are not outside this plan: the state summary says septic homes can connect “when they are ready,” and the Village’s video says more extensions are being studied to serve nearby unsewered neighborhoods. The customers the summary actually projects are the Village’s own sewer customers: today one business, and within five years, 114 new homes.
For them, the Village’s audited financial statements say who decides:
— Village of Homer Glen Annual Comprehensive Financial Report, year ended April 30, 2025
And the Village’s plan, as the state summarizes it, already projects the number: a flat charge of $105 a month per home in 2030, rising each year to $125 in 2035 — $1,500 a year, which the summary puts at 1.17% of Homer Glen’s median household income. To repay the loan it adds a per-1,000-gallon charge to commercial users and a “proposed Village subsidy”: $561,135 in 2030, falling to $42,859 in 2035 — about $1.9 million over six years, by our sum of its table. The summary does not say where the subsidy money comes from. In February the Village told residents the project would be paid for by “future growth and not current Illinois American Water customers,” through loans, possible grants and “connection fees from new users.” The subsidy is a separate line from customer billing, and neither document says whether it would come from those connection fees or from other Village money. The summary says the Village “will reevaluate the projected user rates once actual costs are known.”
Whatever the final number, it will be set the same way: by six trustees, by ordinance — no referendum, and no Illinois Commerce Commission rate case of the kind that governs Illinois American Water.
What’s actually being built
This project treats sewage (wastewater) only. It changes nothing about where your drinking water comes from: Illinois American Water where it serves, your own well elsewhere. The two are easy to mix up because Illinois American Water also runs three wastewater plants inside Homer Glen — but the Village’s new plant is a separate, Village-owned facility.
The Illinois EPA summary describes a screening structure, an Aero-Mod treatment system, sludge holding tanks, disc filtration, UV disinfection, a building for a laboratory, electrical room and blowers, and a new lift station and force main — north of 159th Street, east of Gougar Road, discharging into Fiddyment Creek. Construction is projected from January 2028 to January 2030.
Why it exists: under a 2018 intergovernmental agreement, Homer Glen, the City of Lockport and the Bonnie Brae–Forest Manor Sanitary District arranged for the flow from the Village’s own Fiddyment Creek sewer to be treated at Lockport’s Bonnie Brae plant. Lockport has given notice that it will end that arrangement on January 1, 2030. Without its own plant, the Village would need another outside provider — a new agreement with Lockport, or Illinois American Water — both for that flow and for the new homes and 159th Street parcels it is planning for; under the current agreement, Lockport had already refused any new connections in 2022.
Exhibit C
The line in the budget
The plant also has a line in the Village’s own budget. On April 22, 2026 the Board adopted its budget for fiscal year 2026-27; inside the Capital Project Fund, account 70-00-85-630, “WWTP PROJECT,” is budgeted at $15,487,279.
It is the largest single line in that budget, and it pays for more than the plant: the Village’s June 10, 2026 bid memo charges the $2,591,009.72 Cedar Road sewer extension to the same account. A draft presented five weeks earlier, on March 18, listed the plant and the Fiddyment Creek sewer work as separate projects — “WWTP - EST. (Construction & engineering)” at $14,871,000 and “FIDDYMENT CREEK (Construction & engineering)” at $2,097,148. The adopted budget reports by account, not by project, so those project lines do not appear in it.
Being precise about what this figure is: it is one account in one year’s budget, holding construction money for the plant and the Cedar Road sewer together, in a year that ends in April 2027 — before plant construction is scheduled to begin in January 2028. The Illinois EPA summary in Exhibit A puts the loan project — the plant plus a new lift station, force main and outfall — at $15,968,320.
On page 34 the plant appears only as “WWTP PROJECT,” and because the adopted budget is posted as a scan with no searchable text, even that can’t be found by searching. The Illinois EPA pages in the hearing packet are scans too. Figures from those scans were read off the page images, and the budget lines were checked against the budget’s printed totals; the six-year subsidy figure is our own sum of the state summary’s table. The other figures come from Village records (Board packets and minutes, budget drafts, the audited annual financial report and meeting videos) and news reports, all linked in the sources.
Where the idea came from
The Village has told residents it chose to build after a “detailed feasibility study and cost-benefit analysis.” Neither that study nor the September 2025 project plan is on the plant’s page on the Village website, and we haven’t found any Village communication that lays the options Lockport offered side by side, with their costs, for residents. Here’s what we found going back through the record.
The trouble was on the record by the fall of 2022. On September 28, 2022, the Board heard that Lockport’s Bonnie Brae plant was degrading rapidly; on October 26, 2022, then-Village Manager Carmen Maurella read the Board an email from Lockport: Lockport would not authorize any new connections or additional growth for Homer Glen. On January 11, 2023, under then-Mayor George Yukich, the Board voted 5–0 to fund an $18,250 Robinson Engineering feasibility study of a Village-owned treatment plant. That spring, before the April 2023 election, Maurella announced in the Village’s own Spring/Summer 2023 newsletter that he had put a team together to pursue a Village-owned facility, and trustee candidate Ruben Pazmino — running against Christina Neitzke-Troike’s slate, not with it — said in an April 3, 2023 election preview: “There was always an understanding that the Village would eventually develop its own system.” The idea predates this administration: the Board under Mayor Yukich voted 5–0 to fund the study (Pazmino, who was running against Neitzke-Troike’s slate, seconded it), the Village Manager announced the team, and the Board seated after the 2023 election — which kept three of those five yes votes — carried it forward.
How we got here
Where the decisions were made
Mayor Neitzke-Troike “addressed the wastewater treatment issue and noted that most of the discussions take place in executive session.”
“…three big topics residents keep asking about, unfortunately, some information can not be discussed publicly at the moment.”
The Village Board’s own minutes are unusually direct about this. On February 15, 2024, the minutes record that Mayor Neitzke-Troike “addressed the wastewater treatment issue and noted that most of the discussions take place in executive session,” and asked residents to contact the Village for correct information and “to not believe everything they read on Facebook.” Three months later, on May 8, 2024, the minutes record her saying Illinois American Water, the wastewater project and 143rd Street were “three big topics residents keep asking about, unfortunately, some information can not be discussed publicly at the moment.”
Closed session is lawful and ordinary for buying land — nobody should pretend otherwise, and the Village was in the middle of a $4 million land deal whose price was voted in open session in June 2024. The problem is what came after. Residents were told by a trustee that this was the Village’s top priority, told by the Mayor that some of it couldn’t be discussed publicly, told not to believe everything they read on Facebook — and none of the follow-ups explained the bill or the subsidy. The Village’s February 2026 video says the plant will be paid for by “future growth and not current Illinois American Water customers”; it never mentions a subsidy. At the July 2026 hearing the state summary was part of the packet, but nobody said the projected bill or the subsidy out loud. They sit in a scanned state document in the packet.
And at that same February 2024 meeting, Trustee Rose Reynders described — in one report, recorded in the minutes — a choice the Village has not laid out for residents in any document since: Lockport had given the Village three options — build its own plant, sign a new agreement with Lockport, or go with Illinois American Water for sewage treatment. Homer Glen chose to build. That may have been the right answer. It was still a decision among three, with real tradeoffs, and residents were never walked through them.
What’s still unanswered
Much of what this page once listed as unknown turns out to be on paper, in the Illinois EPA summary. This is what genuinely remains open:
- Where the “proposed Village subsidy” comes from — $561,135 in 2030, about $1.9 million through 2035 — and how it squares with the Village’s word that growth pays for the plant
- Who pays while the plant fills up? — its first phase is sized for about 2,500 residents (the Village’s video), but the state summary projects 114 new homes and one business within five years, and its subsidy shrinks from $561,135 to $42,859 by 2035 on revenue the summary doesn’t explain. What happens to the bill and the subsidy if connections come slower?
- The final cost — $15,968,320 is an estimate, and the Illinois EPA summary says the Village “will reevaluate the projected user rates once actual costs are known”
- Whether homes on septic could ever be required to connect — the state summary says they can connect “when they are ready” and no Village ordinance we have found requires it, but a state rule generally bars approving a new or renovated septic system when a permitted sewer is available within 300 feet, with limited exceptions (77 Ill. Adm. Code 905.20(e))
Questions & answers
Is the Village taking over my drinking water?
Who is the plant actually for?
Why does Homer Glen need to build its own plant at all?
Whose idea was this?
So did the current administration start this project?
Has Mayor Neitzke-Troike talked about this project?
Is this connected to the Badger rezoning near Cedar Glen?
What has the Village said this will cost?
Will my sewer bill go up?
Could I be required to connect if I’m on a septic system?
Why wouldn’t residents get a vote on something this size?
Was there ever a choice, or did this have to happen?
What does Heidi think should happen?
- Illinois EPA — Project Summary and Preliminary Environmental Impacts Determination for the Village of Homer Glen’s loan application (Loan Project L177782, New Wastewater Treatment Facility), dated June 16, 2026 — scanned pages 5–10 of the Village’s July 8, 2026 Board packet. Project cost estimate $15,968,320; 20-year Water Pollution Control Loan at an estimated 2.16%, about $983,960 a year; repayment through customer billing and “a proposed Village subsidy”; projected residential rate $105/month (2030) to $125/month (2035); projected customers “114 residential connections, 1 commercial customer”; septic users may connect “when they are ready.” homerglenil.org (PDF, 147 pp.)
- Robinson Engineering for the Village of Homer Glen — “Wastewater Treatment Facility Feasibility Analysis,” June 29, 2023 DRAFT, posted on the Village website (p. 3: developers had approached the Village, which was “limited in its ability to process development applications” without “economical and long-term infrastructure being readily available”; p. 6, Table 1, “Anticipated Short Term Population Growth in Service Area”: a “Conceptual Site Plan showing 114 residential Lots, no commercial” on 50 acres, 159th Street east of Cedar Road, called “a possible short-term forecast of development”). homerglenil.org (PDF)
- Village of Homer Glen — “Wastewater Treatment: A Plan For Homer Glen,” video narrated by Village Engineer Brett Westcott, posted February 25, 2026 (first phase serving “about 2500 residents”; about 3,000 acres at full buildout; funding from “low-interest loans, potential federal grants, and connection fees from new users”; “paid for by future growth and not current Illinois American Water customers”; no cost, bill or subsidy figure). Quotes from the video’s captions. youtube.com
- Village of Homer Glen — “Homer Glen Water Treatment Vision,” the plant’s own page under Water & Sewer Service (the roadmap document and the February 2026 video; no cost, bill or subsidy figure). homerglenil.org
- Village of Homer Glen — Village Board meeting video, July 8, 2026 (public hearing: HR Green’s Ravi Jayaraman; resident Mike McGee; Village Engineer Brett Westcott on the service area). youtube.com
- Village of Homer Glen — ADOPTED Budget, Fiscal Year May 1, 2026 to April 30, 2027 (adopted April 22, 2026). Capital Project Fund, account 70-00-85-630 “WWTP PROJECT,” $15,487,279, printed page 34. This PDF is a scan with no searchable text layer. homerglenil.org (PDF)
- Village of Homer Glen — FY27 Budget Draft 1 (Admin & Finance Committee workshop, March 18, 2026) and Draft 2 (the April 8, 2026 public-hearing draft): “WWTP - EST. (Construction & engineering) $14,871,000” and “FIDDYMENT CREEK (Construction & engineering) $2,097,148.” homerglenil.org (Draft 1, PDF)
- Village of Homer Glen — FY27 Budget Draft 2, the April 8, 2026 public-hearing draft, with the same Capital Project Fund project lines. homerglenil.org (Draft 2, PDF)
- Village of Homer Glen — Committee of the Whole packet, September 24, 2025 (capital-projects list: “WWTP - EST. (Construction & engineering) $10,728,463”). homerglenil.org (PDF)
- Village of Homer Glen — Village Board packet, April 24, 2024: FY2024-25 final budget report, account 70-00-85-630 “WWTP PROJECT,” $14,095,000. homerglenil.org (PDF)
- Village of Homer Glen — Committee of the Whole meeting video, September 24, 2025 (the plant described as “about $15 million that we have budgeted in its entirety”). youtube.com
- Village of Homer Glen — Village Board packet, June 10, 2026: award of the $2,591,009.72 Austin Tyler Construction bid for the Cedar Road Fiddyment Creek Sanitary Sewer Extension, “to be paid out of 70.00.85.630”; $500,000 grant “pending substantial completion by October 30th, 2026”; the extension “will assist in providing new users” for the planned plant. homerglenil.org (PDF)
- Village of Homer Glen — Village Board packet, January 22, 2025: the HR Green agreement for the plant’s Project Plan (“so the Village of Homer Glen can begin treating the wastewater generated in the Fiddyment Creek service area by the Year 2030”) and Strand Associates’ competing proposal (January 2, 2025), which describes that area as “a largely undeveloped area of the village generally bound by 151st Street, 159th Street, Gougar Road, and Parker Road.” homerglenil.org (PDF)
- Village of Homer Glen — Annual Comprehensive Financial Report, year ended April 30, 2025 (audited). Source for the enterprise-fund rate-setting language, the $50,000 land option and $4,000,000 purchase, and the $64,320 HR Green Waste Water Facilities Plan approval. homerglenil.org (PDF)
- Village of Homer Glen — Village Board minutes, September 28, 2022 (the Board is told the Lockport agreement runs to 2030 and that Lockport’s Bonnie Brae plant is degrading rapidly). homerglenil.org (PDF)
- Village of Homer Glen — Village Board minutes, October 26, 2022 (the Village Manager reads Lockport’s email refusing new connections or additional growth for Homer Glen). homerglenil.org (PDF)
- Village of Homer Glen — Village Board minutes, January 11, 2023 (5–0 vote to fund a Robinson Engineering feasibility study “to evaluate and estimate costs for the construction of a wastewater treatment facility”; the $18,250 proposal is in that night’s packet). homerglenil.org (PDF)
- Village of Homer Glen — Spring/Summer 2023 newsletter, “Carmen’s Corner” (p. 3, Village Manager Carmen Maurella’s column announcing the wastewater-facility team). homerglenil.org (PDF)
- Patch — “2 Slates Face Off For Homer Glen Village Trustee, Clerk: Election 2023” (Ruben Pazmino quote, April 3, 2023). patch.com
- Patch — “Lockport Will Terminate Waste Water Agreement With Homer Glen In 2030” (April 20, 2023). patch.com
- Patch — “New Homer Glen Mayor, Trustees Sworn In Wednesday” (posted April 27, 2023; reports that Neitzke-Troike and new trustees were sworn in on April 26, before a Board meeting that had been expected to be Yukich’s last). patch.com
- Patch — Homer Glen Village Manager resignation coverage (August 2023). patch.com
- Village of Homer Glen — Village Board meeting packet, June 12, 2024, containing the approved minutes of the February 15, 2024 and May 8, 2024 Board meetings (Trustee Reynders on Lockport’s three options; Mayor Neitzke-Troike on executive session and on information that “can not be discussed publicly”). homerglenil.org (PDF)
- Village of Homer Glen — Village Board packet, March 24, 2021: staff memo on Ordinance 21-016 (Village water and sewer rates), whose non-metered rates apply to homes on well and septic “that choose to connect to the Village’s sanitary sewer system.” homerglenil.org (PDF)
- Village of Homer Glen — Major Contracts & Agreements register (HR Green site study, land purchase, Project Plan agreement). homerglenil.org
- Village of Homer Glen — “Homer Glen’s Waste Water Treatment Plant and Visions for the Village” (Village roadmap document; names Robinson Engineering for the feasibility study, states the ~1 acre per MGD sizing rule, and raises a temporary “pop-up” plant as a contingency). homerglenil.org (PDF)
- Village of Homer Glen — news item, “Wastewater Treatment Plan,” February 25, 2026. homerglenil.org
- Village of Homer Glen — Village Projects page (updated July 9, 2026; lists six projects, none of them the wastewater plant or the Cedar Road sewer extension). homerglenil.org
- Village of Homer Glen — detailed history of lake water and sewer service. homerglenil.org
- Village of Homer Glen — Mayor’s Office (confirms “Village President,” commonly called Mayor). homerglenil.org
- Patch — “Homer Glen Approves $2.5M Sanitary Sewer Line Project” (published June 11, 2026, reporting the Board’s June 10 vote on the $2,591,009.72 Austin Tyler Construction bid). patch.com
- Illinois Administrative Code, 77 Ill. Adm. Code 905.20(e) (Private Sewage Disposal Code): new or renovated private sewage disposal systems “shall not be approved” where a sanitary sewer operated under Illinois EPA permit is available — for a residential property, generally within 300 feet, with exceptions for physical barriers, local ordinances and connections an individual line can’t make. ilga.gov
- Map: Village boundary and road positions © OpenStreetMap contributors, available under the Open Database License (openstreetmap.org/copyright). The service area is drawn approximately from the Village’s own descriptions, not from a parcel map. openstreetmap.org
Stay informed
We’ll update this page as the subsidy’s source, the new plant’s sewer rate and the septic answer become public.