Heidi For Homer

Homer Glen · ComEd Goodings Grove Substation

ComEd wants to build the tallest building in Homer Glen

It would go on Bell Road, just south of 143rd Street, where ComEd has had a power station since about 1970. The main building would be almost 59 feet tall and nearly the length of two football fields. Village rules for this kind of building stop at 35 feet. The Village announced the plan once, in a five-sentence notice, and the Plan Commission has already voted to recommend it.

59 ft
How tall
The main building — 58 ft 8 in
35 ft
What rules allow
Village Code, for this kind of building
9
Rule exceptions asked for
Height, setback, wall, parking and more
4–1
Plan Commission vote
Recommended approval, July 2, 2026
67 ac
Size of the property
ComEd has been there since about 1970
What should the Village do? Two quick questions at the bottom of this page — see how your neighbors are voting.

The short version

Homer Glen needs electricity that stays on. The equipment at this power station is more than 50 years old, and ComEd says some of it is worn out. Replacing it is a real need, and Heidi is not asking anyone to cancel this project.

But this is the biggest building the Village has ever been asked to approve, and almost nobody in Homer Glen heard about it. The Village posted one short notice. ComEd held an open house and seven people came. The commissioners who voted on it said they had the plans for six days.

A project can be necessary and still be handled badly. Homer Glen deserves to be told.

First: what is a substation?

Power plants make electricity far away. To get it to your house, it travels on very big wires at very high voltage. A substation is where those big wires meet. It switches power from one line to another and steps it down so it can keep going toward homes and businesses.

Think of it like a train station. Trains do not get built at the station — they stop there, switch tracks, and head somewhere else. That is what this place does with electricity.

Nothing here makes power, and nothing here is nuclear. There is no nuclear material at this site. ComEd’s own words for it are “the Goodings Grove Transmission Substation.” Transmission means the big long-distance wires.

So where does the electricity come from? From many places at once. Nuclear plants make about half the electricity produced in Illinois, more than any other state makes, and the closest one — Braidwood — is right here in Will County. Wind farms, natural gas plants and other sources feed the same grid. One of the power lines that ends at this Bell Road site is actually named for a wind farm. Once it is all on the grid, it mixes together. You cannot point at a wire and say which plant that electricity came from.

HOMER GLENLOCKPORTLEMONTORLAND PARKTINLEY PARKMOKENA143RD ST163RD STBELL RDBLUE ISLAND345 kV + 138 kVWILL COUNTYgenerating station — 138 kVELWOOD · BLACKSTONE WIND FARM345 kV — southwestEAST FRANKFORT345 kV — southBEDFORD PARK345 kV + 138 kV — northeastCRAWFORD, CHICAGO345 kV — northGOODINGS GROVEsubstation · 14546 S. Bell Rd345,000-volt line138,000-volt lineLocal roadPower line geometry © OpenStreetMap contributors
Nine named high-voltage power lines end at this one spot — on Bell Road between 143rd Street and 163rd Street. The dashed gold lines carry 345,000 volts; solid gray lines are local roads. That is why ComEd calls Goodings Grove “a critical part of the regional transmission system” — power crossing this site is headed for Blue Island, Bedford Park, East Frankfort, and Crawford in Chicago, not just Homer Glen. Line names, voltages and routes from OpenStreetMap; the substation is tagged there as ComEd Goodings Grove 138kV–345kV Substation, operator Commonwealth Edison.

Why this spot matters

Nine big power lines end at this one property. Five of them carry 345,000 volts, which is about as high as power lines go. They run toward Blue Island, Bedford Park, East Frankfort, Elwood, and Crawford in Chicago.

That is why ComEd calls it “a critical part of the regional transmission system.” The power crossing this site is not just Homer Glen’s power. ComEd’s project manager told the Plan Commission that the way the station is wired today, one broken piece of equipment could knock out whole transmission lines at once.

25 ft50 ft75 ft100 ft125 ft~25 ftA two-storyhousefor scale35 ftWhat the rulesallow hereVillage Code25 ft 9 inComEd's secondbuildingalso proposed58 ft 8 inComEd's mainbuildingmeasured from average ground64 ft 8 inIts tallestsidethe north face133 ftThe nearbywater towerfor scaleIt would be the tallest building in Homer Glen.Village Planning Director Chris Gruba said so on the record, July 2, 2026
The rules for this kind of building in Homer Glen stop at 35 feet. ComEd asked for 58 feet 8 inches — and the north side of the building, where the ground is lower, would stand 64 feet 8 inches. Village staff said one other part of the code may allow up to 60 feet, so the height is being handled as one of nine exceptions to the rules. All figures from the Village of Homer Glen Plan Commission minutes of June 18 and July 2, 2026, case HG-2518-SPPUD.

What ComEd wants to build

  • A main building 58 feet 8 inches tall, about 82 feet wide and 515 feet long — nearly two football fields end to end. It has two floors, about 84,000 square feet inside.
  • A second building, 25 feet 9 inches tall, built in two stages.
  • A wall 12 feet 6 inches tall around part of the site, made of stone-look block, with a foot of barbed wire on top. Today that edge is mostly mesh fence.
  • Taking out 11 power poles and putting up 21 new ones. The old lattice towers get replaced with single poles. Village rules do not cover these — the Village cannot say no to them.
  • A bigger stormwater pond, a new driveway off Bell Road, and 158 new trees and 303 shrubs.
  • A small rest area at the southeast corner by the bike path, with a bench, a bike rack, a shade structure and a butterfly garden.

The equipment goes inside a building instead of sitting out in the open. ComEd says that protects it from storms and takes up less land than spreading it across a field.

The nine rules it asks to skip

To build this, ComEd needs the Village to make exceptions to nine of its own rules. This is the part almost nobody has seen.

The ruleWhat it saysWhat ComEd asks for
How tall the main building can be35 feet58 feet 8 inches
How far it must sit from the south property line118 feet97 feet
How much green space along Bell Road30 feet12 feet
A wall in the front yardNot allowed at allA 12 ft 6 in wall
How tall a wall can be on the sides and back6 feet12 feet 6 inches
Parking spaces8 required0 proposed
Loading spaces3 required0 proposed
Parking surfaceMust be a hard surfaceGravel
Signs on fencesNot allowedRequested
About the parking: nobody works at this station day to day. ComEd says crews drive right up to the equipment and that paving the ground would make it harder to dig up when something breaks. Village staff said the Village can waive the eight regular spaces, but it cannot waive the accessible parking space or the accessible restroom — only the State of Illinois can do that.

How we got here

Late 1960s – early 1970s
ComEd builds the Goodings Grove substation on Bell Road. Much of the equipment inside is still the original equipment.
2010 – 2012
ComEd expands the equipment enclosures at the substation.
2015
ComEd upgrades the fence to meet national security standards and adds landscaping.
2022
ComEd decides the substation needs to be expanded to keep the power reliable.
February 2025
ComEd and Village staff start talking about the project. These talks go on for about a year and a half before the public hearing.
January 2026
ComEd presents the project to the Village Board at a Committee of the Whole meeting.
June 3, 2026
The Village posts a short notice on its website saying ComEd wants to upgrade the substation. It is five sentences long. As far as we can find, the Village has not posted anything else about the project since.
About June 11, 2026
ComEd holds an open house for neighbors who got hearing notices. Seven people come.
June 11 & 16, 2026
Two neighbors write in with questions and concerns. Two county groups write in to support the project.
June 18, 2026
The Plan Commission opens the public hearing. Chairman Hand says the commissioners only had the plans for six days. The hearing is held open and continued.
July 2, 2026
The Plan Commission votes 4 to 1 to recommend approval, with five conditions. Commissioner Stanly votes no.
Still ahead
This was only step two of four. The Village Board still has to approve the preliminary plan — and as of late August 2026, the case had not yet appeared on any Village Board agenda (we checked the July 22, August 12 and August 26 agendas page by page). After that, the Plan Commission and the Village Board each have to approve the final plan. Nothing has been built yet.
Through end of 2028
If it is approved, construction trucks would use Bell Road and a temporary path across Homer Township land to Founders Crossing. ComEd’s contractor said trucks would be done around the end of 2028.

What neighbors actually said

Four written comments were read into the record at the June 18 hearing. Two came from neighbors, two came from county organizations.

A neighbor who lives directly west wrote that the substation’s lights already shine into his yard, that they are not shielded, and that they go past what the code allows at his property line. He said the lighting changed within the last year. He asked the Village to confirm the lighting follows the rules as part of this approval — and said that with that fixed, and with a nicer wall along Bell Road instead of a fence, he had no objection to the expansion.

Another neighbor asked simple questions that still deserve simple answers: does a building this size fit the image of Homer Glen? What happens inside it? What hours? How much traffic, noise and light?

The Will County Center for Economic Development and the Will County Governmental League both wrote in support, saying the upgrade modernizes a 70-year-old facility and makes the grid more reliable, especially during bad storms. At the hearing, a Carpenters Local 174 representative, the business manager of IBEW Local 9 — a 30-year Homer Glen resident — and a retired power plant engineer who also lives here all spoke in favor.

We are including the support because it is real. Skilled trades want the work, county groups want the reliability, and at least one neighbor said he is fine with it if the lights get fixed. The problem is not that people support it. The problem is how few people knew there was anything to have an opinion about.

Where Heidi stands

Heidi supports upgrading the grid. She is not asking the Village to reject this project. She is asking for five things, and every one of them comes straight out of the Village’s own record.

  • Tell people. One five-sentence notice for the tallest building in town is not enough. Big projects should get real notice, in the newsletter and by mail, before the vote — not after.
  • Answer the lighting complaint. A neighbor said in writing that the lights already break the rules at his property line. That should be measured and answered on the record, not folded into an approval.
  • Make the conditions stick. The Plan Commission asked for the wall to be extended and for a signed letter from Homer Township before construction staging happens. Those need to be real requirements at the final vote, not good intentions.
  • Protect the streets during construction. Trucks would run on Bell Road into 2028. Routes, hours and road repair should be in writing before the first truck rolls.
  • Get a straight answer on cost. ComEd’s own two representatives gave different answers about who pays for this in the same meeting. Residents are entitled to one answer.
The Plan Commission only recommended it. The Village Board still votes, and then the whole final plan goes through both bodies again. There is still time to get the conditions right.

And when the power goes out

This summer showed why any of this matters. On August 11, 2026, storms knocked out power to about 3,270 Homer Glen customers. Two weeks earlier, on July 27, more than 22,000 Will County customers lost power, and ComEd said some would not be back on for four days.

When the power is out, it is not an inconvenience. It is sump pumps that stop, medicine that needs refrigeration, oxygen machines, traffic lights, garage doors, well pumps, and seniors sitting in the heat with no way to call anybody.

As mayor, Heidi will push for the basics after every major outage:

  • A straight answer from ComEd on what failed, how many homes lost power, and how long it took.
  • Village updates that actually reach people, including those who are not on Facebook.
  • A real plan for seniors and residents who depend on medical equipment during long outages.
  • A public follow-up when the same neighborhoods keep going dark.

Questions & answers

Is this a nuclear power plant?
No. Nothing at this site makes electricity, and there is no nuclear material there. A substation is a place where electricity gets switched and passed along, like a train station for power. The power itself is made somewhere else and travels here on big wires.
So where does the electricity come from?
From lots of places at once. Nuclear plants make about half the electricity produced in Illinois — more than any other state makes. The closest nuclear plant, Braidwood, is in Will County, the same county as Homer Glen. But wind farms, natural gas plants and other sources all feed the same grid. One of the power lines that ends at this Bell Road site is even named for a wind farm. Once electricity is on the grid, you cannot point at a wire and say which plant it came from — it all mixes together.
Why does the building have to be so big?
ComEd says two things make it tall. First, a crane runs along the ceiling so workers can lift heavy equipment in and out. Second, the electrical cables get hotter the deeper underground they go, and hot cables cannot carry as much power. So ComEd says it cannot sink the building much further into the hill. The site is the highest point in Homer Glen, and the ground drops about 80 feet from the south end to the north end.
What is the gas inside it?
It is called SF6. ComEd uses it instead of open air to keep the electrical parts apart, which is what lets all that equipment fit inside a building instead of spreading across a field. ComEd says the gas is colorless, has no smell, does not burn, and is sealed inside aluminum tubes. Commissioners asked what happens if it leaks. ComEd said the equipment is watched around the clock and an alarm goes off at their control center right away. They also said the maker guarantees leaks stay under one tenth of one percent.
Will this raise my ComEd bill?
The Village Board chairman asked exactly that at the June 18 hearing, and ComEd's own two representatives gave different answers in the same conversation. Their outside lawyer said there is no special line item and the cost is shared by about 4 million ComEd customers, with the Illinois Commerce Commission checking that the spending is reasonable. Their project manager then said that was not correct — that because the project is part of the regional PJM grid plan, the cost is spread across the 13 states PJM covers. We are reporting both answers because both were given, and nobody settled it that night.
Will it be noisy?
ComEd said there are no new power transformers, which are the parts that hum. The four transformers already on the site stay. There will be air conditioning to keep equipment cool. The equipment is sensitive to shaking, so ComEd says it has to limit vibration anyway. Village staff noted honestly that the noise and vibration standards in the code are hard to check.
What about the lights?
A neighbor who lives directly west wrote in before the hearing. He said the substation lights already shine into his yard, are not shielded, and go past what the code allows at his property line — and that the lights changed within the last year. He asked the Village to confirm the lighting meets the rules as part of this approval. Village staff said the new lighting plan complies. The complaint was about the lights already there.
Did anyone support it?
Yes, quite a few. The Will County Center for Economic Development and the Will County Governmental League both wrote letters supporting it. A representative of Carpenters Local 174 and the business manager of IBEW Local 9 — who lives in Homer Glen — both spoke in favor. So did a 30-year resident who is a retired power plant engineer. This is not a case where everybody is against it.
Can residents still say anything?
Yes. The Plan Commission only made a recommendation. The Village Board has to vote, and then there is a whole second round for the final plan. You can email the Village's Planning and Zoning Department, and Village Board meetings have a public comment period.
What does Heidi actually want?
She does not want to stop the project. Homer Glen needs power that stays on, and the equipment out there is over 50 years old. What she wants is the part the Village skipped: telling residents. One five-sentence notice, an open house that seven people attended, and commissioners who had the plans for six days is not how you decide on the tallest building in town. She also wants the conditions to be real ones — the wall extended, the lighting complaint actually answered, the Township agreement signed before construction, and truck routes that do not turn neighborhood streets into a haul road.

How to speak up

Written comments about this case go to the Village’s Planning & Zoning Department at cgruba@homerglenil.org. Reference case HG-2518-SPPUD, 14546 S. Bell Road. Village Board meetings also have a public comment period, and the agendas are posted at homerglenil.org.

Tell us what you think

Two quick questions. There is no right answer to either one — we want to know what Homer Glen actually thinks, and we will share the results.

Community Poll

Before today, had you heard about ComEd's plan to build the tallest building in Homer Glen?

Current Results

No — this is the first I'm hearing of it0% (0 votes)
I'd heard something, but no details0% (0 votes)
Yes, I followed the hearings100% (1 votes)

1 total vote

And the decision itself. These are the same four choices Village staff gave the Plan Commission the night they voted.

Community Poll

ComEd wants to build what would be the tallest building in Homer Glen — a 59-foot substation enclosure on Bell Road. What should the Village Board do?

Current Results

Approve it — keeping the power on comes first0% (0 votes)
Approve it, but only with stronger conditions100% (1 votes)
Reject it as proposed — too big for this spot0% (0 votes)
Not enough information yet — answer residents' questions first0% (0 votes)

1 total vote

Where this came from
  1. Village of Homer Glen — Plan Commission, approved Minutes of the Meeting on July 2, 2026 (case HG-2518-SPPUD: staff report, ComEd testimony, 4–1 recommendation, five conditions, Commissioner Stanly's dissent on Special Use Standards #2 and #3). homerglenil.org (PDF)
  2. Village of Homer Glen — Plan Commission, approved Minutes of the Meeting on June 18, 2026 (building dimensions, the nine PUD exceptions, the 133-foot water tower comparison, all four written public comments read into the record, the SF6 questions, the ratepayer-cost exchange, and the motion to continue the hearing). homerglenil.org (PDF)
  3. Village of Homer Glen — News Flash, “ComEd Project,” posted June 3, 2026 (the Village's only public announcement of the proposal; hearing date and written-comment address). homerglenil.org
  4. Village of Homer Glen — Plan Commission agendas and minutes archive (for the July 16 and August 6, 2026 meetings and anything filed after this page was written). homerglenil.org
  5. Village of Homer Glen — Village Board agendas and minutes archive. We searched the full July 22, August 12 and August 26, 2026 agenda packets; case HG-2518-SPPUD appears in none of them, so the Board's preliminary-plan vote had not been scheduled when this page was written. homerglenil.org
  6. OpenStreetMap — the site is mapped as “ComEd Goodings Grove 138kV–345kV Substation,” substation type “transmission,” operator Commonwealth Edison. The nine named power-line corridors on the map above (Elwood, Blackstone Wind Farm, East Frankfort, Bedford Park, Crawford, Blue Island, Will County Generating Station) come from the same data. openstreetmap.org
  7. Patch — “Over 9,000 Without Power In Homer Glen, Lockport After Severe Storms” (August 11, 2026: 3,270 Homer Glen customers out). patch.com
  8. Shaw Local / The Herald-News — “Storms knock out power to thousands of Will County ComEd customers” (July 27–28, 2026: more than 22,000 Will County customers out). shawlocal.com
  9. U.S. Energy Information Administration — Illinois State Energy Profile (Illinois generates more electricity from nuclear power than any other state). eia.gov

Keep me posted

We’ll update this page as the Village Board acts on it.

← All IssuesWastewater PlantWater Rate Fight151st Street Widening